Corning Incorporated
Headquarters Expansion
Corning
Incorporated creates leading edge technologies for the fast growing
segments of the world's economy. Sullivan Park is their premier
research and development center located on 1000 acres in Erwin,
NY. It was an honor to be chosen the construction manager for the
complete replacement of their underground high voltage network.
We met the challenge of an extremely tight schedule and the requirement
to tie in all the existing substations without any power disruption
to Corning's processes or critical experiments. Through careful
planning and customer communications, the project was completed
on time and without any disruptions to the research facility.
Services
performed:
-
Dual-ended, outdoor 12.5 KV receiving station and tie breaker
installed, including four sets of 500 MCM, 15 KV, copper conductors
encased n ductbank from utility substation 2000 feet away
- More
than 50 15 KV feeder cable and a 120 volt battery back-up system
installed, including construction of a 24'x32'x8' concrete vault
to house them
- More
than 3000 feet of ductbank, manholes, and conductors installed
to feed the 14 existing indoor substations
- Cable
splicing and termination
- High
potential testing
- Computerized
monitoring network installed for centralized reporting
- Construction
of a paved access road

|